Slab pre-pour inspection in Marsden Park

Barrier, steel and formwork, in the hours before any of it becomes concrete.

  • The day before the pour, steel and formwork complete
  • About 1 hour on site
  • Report within 24 hours
Price your Marsden Park inspectionGive us the address and the stage.

Fully licensed & accredited

Stage2 of 7
When to bookThe day before the pour, steel and formwork complete
Time on siteAbout 1 hour on site
Inspected againstAS 2870, AS 3600, NCC Part 3.2, the engineer's slab design and the soil report

What is included in a Marsden Park slab pre-pour inspection

  • Slab class and layout checked against the engineer's design and the soil report
  • Edge beam and internal beam depths and widths
  • Reinforcement size, spacing, laps and trench mesh
  • Bar chairs, cover and support so steel does not sit on the ground
  • Waffle pods, void formers and pod spacing
  • Vapour barrier coverage, laps and tape at penetrations
  • Plumbing and electrical penetrations and sleeves
  • Set-downs for wet areas, garage, porch and alfresco
  • Termite management components installed before the pour
  • Formwork alignment, level and set-out against the plans
  • Stormwater pipe cover and pit positions where visible
  • Site cut, fill and pier holes where visible
  • Hot water service and meter box slab extensions formed
  • Trench cleanliness and debris before the pour
Why it matters here

Slab pre-pour inspections on Marsden Park builds

The Marsden Park slab findings concentrate on the vapour barrier: not carried beneath the whole slab on one job, and punctures left unsealed on another. That layer only performs as one continuous membrane, so a gap at the edge and an untaped puncture amount to the same thing. Add cover below the minimum, beam widths varying and bar placement to check, and everything on the list stops being verifiable the moment the truck leaves.

What we find at this stage in Marsden Park

  • Vapour barrier not carried beneath the entire slab
  • Punctures not sealed with polyethylene tape
  • Concrete cover below the minimum
  • Beam widths inconsistent through the raft
  • Bar placement and internal ribs to be confirmed
Internal rib before the pour, Marsden Park
Internal rib before the pour
Sample findings

Sample defects found during our slab pre-pour inspections in Marsden Park

Annotated findings from Slab pre-pour inspections on Marsden Park builds. Client addresses withheld.

Barrier not extended beneath the entire slab, recorded during a slab pre-pour inspection in Marsden Park
Barrier not carried to the slab edge
Punctures not sealed with polyethylene tape, recorded during a slab pre-pour inspection in Marsden Park
Punctures left unsealed
Insufficient concrete cover, recorded during a slab pre-pour inspection in Marsden Park
Cover below the minimum
Beam width inconsistent, recorded during a slab pre-pour inspection in Marsden Park
Beam width varying

The other stages of a Marsden Park build

  1. Bored piers inspection in Marsden Park1Bored piersAfter boring and cage placement, before concrete
  2. Frame inspection in Marsden Park3FrameOnce frame and trusses are up and the roof is on, before lining
  3. Lock-up (pre-plaster) inspection in Marsden Park4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
  4. Fixing inspection in Marsden Park5FixingAfter mouldings, doors and joinery, before the painter
  5. Waterproofing inspection in Marsden Park6WaterproofingAfter the membrane is applied and before any tile is laid
  6. Pre-handover (PCI) inspection in Marsden Park7Pre-handover (PCI)Two to three weeks before your handover date

All construction stage inspections in Marsden Park →

Guides

Construction stage guides for Marsden Park

All guides →

Book a slab pre-pour inspection in Marsden Park

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Slab pre-pour inspections in Marsden Park: common questions

Why does one puncture matter?

Because the barrier works only as a continuous layer. A single unsealed puncture is a direct path for ground moisture into the slab, and it costs a strip of tape to close.

Does looking at a poured slab help?

You can see the surface. Cover, the steel within and the barrier beneath are all beyond reach once concrete is placed.

And if the pour moves back?

The booking moves with it and nothing extra is charged. Programmes move constantly.

What duration is the site visit?

An hour to ninety minutes on an ordinary lot, with the report generally out that evening.

What is an internal rib?

The concrete beam running between waffle pods inside the raft. Its width and its steel are what give the slab its stiffness.

What documents should I provide?

Your lot's engineering and the soil report behind it.